The Federal Aviation
Administration (FAA) requires a permit on construction cranes any time that they
will exceed a 100:1 sloped surface from the nearest point of the nearest runway
out to 20,000 feet or 200 feet AGL (above ground level) beyond.
The FAA requires that
Form 7460-1 be submitted at least 30 days before or more either before
the date the proposed construction is to begin, or the date an application
for a construction permit is to be filed.
For further information and to
file the form click on the following link:
https://oeaaa.faa.gov/oeaaa/external/portal.jsp
Also please check with
Federal, State and Local Governments for any forms or permits that are also
required. For more information please contact the FAA
or refer to Federal Aviation Regulations Part 77.